Hedgewood Properties Research Project
Introduction
Hedgewood Properties, Inc. has been a Building
America builder partner with IBACOS since 1999.
They build approximately 200 homes a year in
communities north of Atlanta, Georgia. All of
their homes meet EarthCraft House™ guidelines,
which are a blueprint for healthy, comfortable,
affordable homes that cut energy and water bills
and protect the environment. The Southface Energy
Institute, a technical partner on the project,
administers the EarthCraft House™ program. Hedgewood’s
homes are typically two stories with over 3,000
square feet of floor area and may have a full
basement, crawl space or slab-on-grade foundation.
Detached garages are a common feature.
Builder Standard House Characteristics
Due to Hedgewood’s involvement in the EarthCraft
House™ program, the energy efficiency characteristics
of their homes are well documented. We obtained
information through the Southface Energy Institute
to define the Builder Standard House. The house
is considered representative of Hedgewood homes
in the region where the pilot home is being built.
The information can be summarized as follows: |
| Building Envelope |
| • |
Due to the recent building code changes, the
use of low solar heat gain windows has become mandatory.
Hedgewood uses windows that are wood-framed, double-glazed,
with low-emissivity coating; U=0.35 and SHGC=0.34. |
| • |
The profile of exterior walls include: cladding
material, housewrap, structural sheathing, 2x4
framing, R-13 kraft-faced fiber glass insulation
batts in cavities, and drywall finish. Band joists
are insulated with R-13 blown cellulose insulation
batts in cavities. Brick, stone and fiber cement
siding are common claddings. |
| • |
Basement foundation walls are typically framed
and insulated with R-13 unfaced fiberglass batts
unless the area is to be finished in which case
drywall is installed around the interior wall perimeter.
Penetrations through the wall can provide pathways
for humid air to reach the concrete foundation
wall and condense. |
| • |
Blown-in cellulose insulation is used in the
attic to achieve R-38. Unfaced R-19 fiber glass
batt insulation is used in the floor of living
space over the garage and floors over unconditioned
spaces. Roofs have asphalt shingles. |
| • |
There is an opportunity to improve flashing around
windows and doors. The long-term durability of
exterior walls could be compromised because of
inappropriate flashing product usage, poor flashing
techniques and inadequate integration with the
drainage plane. |
| • |
In order to meet EarthCraft House™ guidelines,
homes require an average air-change rate resulting
from natural infiltration lower than 0.35 ACH.
Troublesome airflow pathways include overhanging
fireplaces, attic chases, knee walls adjacent to
attic space and penetrations through exterior walls.
The main air barrier, which is the interior drywall,
is usually not continuous in ceiling and exterior
wall locations. |
| |
|
| Mechanical System |
| • |
Heating equipment uses natural gas and has an
efficiency of 80% AFUE and is B-vented. In most
homes there are two air handlers, with at least
one in the attic. Cooling equipment has an efficiency
of 12 SEER, and either 4- or 5-ton capacity (depending
on house size) units are usually installed. |
| • |
To meet EarthCraft House™ guidelines total air
distribution system air leakage must have a value
less than 5% of the total floor area. For a 3,000
square foot house this amounts to 150 cfm of air
leakage. Floor registers and ductwork traveling
through the basement serves the first floor. Ductwork
serving the second floor travels through vented
attic space to second floor ceiling delivery locations. |
| • |
The hot water heaters use natural gas and typically
have a 50-gallon capacity and an energy factor
of approximately 0.52. |
| • |
An insulated duct connects outdoor air to the
air handler return air plenum and provides mechanical
ventilation. The outdoor air is drawn into the
air distribution system when the air handler operates.
A mechanical damper is often placed in the duct
that homeowners are asked to close on warm humid
days. Exhaust fans in bathrooms remove odors and
moisture when switched on. |
| • |
Dedicated return air ductwork is common for all
bedrooms. |
| • |
Lighting fixtures predominately use incandescent
lamps. Appliances have typical energy efficiency. |
| |
|
Analysis of Builder Standard Characteristics
Based on the information provided and our observations,
we determined that several opportunities exist
for improving the builder’s standard practice.
These include: |
| • |
Using a basement foundation wall system that
has improved thermal performance and prevents condensation
from occurring at the foundation wall. |
| • |
Improving building airtightness practices to
eliminate comfort problems associated with drafts
and uneven temperatures. |
| • |
Optimizing the HVAC system with higher efficiency
equipment so that it more efficiently provides
comfortable temperature and humidity conditions. |
| • |
Improving the efficiency of hot water production. |
| • |
Providing mechanical ventilation to maintain
good indoor air quality and comfortable conditions
on a consistent basis. Humid outdoor air used for
ventilation cannot cause discomfort. |
| • |
Using energy efficient lighting to reduce energy
consumption and increase comfort during cooling
conditions. |
| • |
Using energy efficient appliances to reduce energy
consumption. |
| • |
Optimizing window and door flashing products
and techniques and integrating them effectively
with the drainage plane to increase home durability. |
| |
|
Pilot Home Characteristics
The builder decided that the model home in their
new Westbrook community near Cumming, Georgia,
would be the best candidate to be the pilot home
since it would be able to showcase publicly the
most advanced system technologies for the longest
time. The pilot home was designed to achieve
a minimum of 40% savings in total energy use
and supply some of its electrical energy via
a photovoltaic system. The home has a total of
3,643 square foot of finished floor area spread
over two stories and a basement and is accompanied
by a detached garage. This plan typically has
two air handlers. With the input of the builder,
IBACOS developed detailed final specifications
for the home that are summarized as follows: |
| |

Figure
1. Pilot home during construction. It has a front
access, walk out basement. The front of the home
faces east. |
| |
|
| Building Envelope |
| |
Windows are the same as used for all of the
builder’s homes. They are wood-framed, double-glazed,
with a low-emissivity coating with U=0.35 and SHGC=0.34. |
| |
The exterior walls consist of exterior sheathing
comprised of R-3 (½ in. thick) extruded
polystyrene rigid board insulation sheathing or
OSB structural sheathing. House wrap covers the
sheathing material to enhance water drainage. Cellulose
spray insulation provides R-13 thermal performance,
within 2x4 exterior wall assemblies and band joists,
and R-19 thermal performance for 2x6 exterior wall
assemblies, which are located in the basement. |
| |
Unfinished sections of basement walls will be
insulated on the inside with R-8 (1¼ in. thick)
polyisocyanurate foam board insulation glued directly
to the foundation wall. An interior 2x4 framed
wall will be adjacent to the foam board insulation
and its cavities will contain cellulose spray-in
insulation (R-13 thermal performance). |
| |
The air-change rate due to natural infiltration
will be a maximum of 0.35 ACH. To improve building
airtightness, emphasis will be placed on draftstopping
large holes to ensure air barrier continuity. In
particular, draftstopping will be conducted at
exterior wall and ceiling locations where no cellulose
insulation will be installed. This includes areas
such as behind tubs, the overhanging fireplace,
and duct chases. The numerous penetrations through
the envelope will need to be sealed as well. |
| |
Long-term durability of the building shell will
be enhanced with the greater use of flashing and
rainwater control measures. Flexible flashing membrane
will be used around window and door rough openings
and integrated with the drainage plane. |
| |
Blown-in cellulose insulation will be used in
the attic to the R-38 level. |
| |
|
| Mechanical |
| |
One direct vent natural gas furnace with 94%
AFUE, 120.0 MBH input, 1900 cfm (high fan speed
@ 0.60 in. ESP) design airflow will be used and
located in the basement. A 14 SEER, 5-ton capacity
condensing unit will provide cooling. |
| |
Hot water is provided by a two natural gas fired
tankless units each with 175 MBH input and an energy
factor of 0.82. The units will be direct vented. |
| |
Total air distribution system air leakage target
is 10% of system airflow (190 cfm) with air leakage
to the outside less than 5% of system airflow (95
cfm). As much of the sheet metal and insulated
flex ductwork as possible will be located within
the conditioned space of the home. A central, fully-ducted
return system will serve each floor with dedicated
return air ductwork serving each bedroom to keep
room pressures balanced. |
| |
A ventilation dehumidifier provides mechanical
ventilation. The system will run continuously drawing
outdoor air at a maximum flow rate of 220 cfm (@
0.10 in. ESP), which is dehumidified before entering
the supply air trunk. ASHRAE 62.2 ventilation requirements
for the house are 70 cfm. |
| |
We recommend that 90% of lighting in the home
should be from fluorescent fixtures, compact, and
linear. |
| |
Appliances meeting Energy Star® requirements
will be used. |
| |
A 2 kW photovoltaic system will be installed
to generate electricity. |
Advanced System Costs and Benefits Energy Use
We used EnergyGauge USA software version 2.1 to calculate
end-use site energy for the Hedgewood Properties pilot
home and to compare the pilot home with the Builder
Standard House (as defined earlier) and the Building
America Benchmark Definition version 3.1. Energy use
values are noted in Table 1 and are based on site orientation
averaged for the four cardinal directions. Total annual
site energy estimates without plug load usage are subtotaled
for easy reference and comparison.
Table 1. Summary of Estimated End-Use
Site Energy for Hedgewood Properties Project DesignAnnual
Site Energy
|
|
BA Benchmark |
Builder Standard Home |
Pilot Home Design |
End-Use |
KWh
|
therms
|
KWh
|
therms
|
KWh
|
therms
|
Space Heating |
561
|
796
|
491
|
676
|
222
|
349
|
Space Cooling |
5532
|
0
|
3958
|
0
|
2406
|
0
|
DHW |
0
|
188
|
0
|
195
|
0
|
89
|
Lighting |
3360
|
0
|
3360
|
0
|
2380
|
0
|
Appliances |
2610
|
-
|
2610
|
-
|
2000
|
-
|
Subtotal |
12062
|
983
|
10419
|
871
|
7008
|
438
|
Plug Loads |
5334
|
-
|
5334
|
-
|
4334
|
-
|
Total Usage |
17396
|
983
|
15753
|
871
|
11342
|
438
|
Site Generation |
-
|
-
|
-
|
-
|
2340
|
-
|
Net Energy Use |
17396
|
983
|
15753
|
871
|
9002
|
438
|
A summary of electric and natural gas consumption components
for various end uses for the pilot home are noted in
Table 2.
| Table 2. End-Use Categories |
| End-Use |
Electric Consumption Component |
Natural Gas Consumption Component |
| Space Heating |
Supply fan during space heating, furnace, gas
ignition system, combustion fan motor, thermostat,
exhaust ventilation fan, ventilation dehumidifier |
Gas burner |
| Space Cooling |
Condensing unit fan and motor, supply fan during
space cooling, thermostat, exhaust ventilation
fan, ventilation dehumidifier |
None |
| DHW |
Power venting system, gas ignition system |
Domestic water heater |
| Lighting |
Indoor lighting, outdoor lighting |
None |
| Appliance |
Refrigerator, clothes dryer, range/cooking, washing
machine, dishwasher |
None |
| Plug Loads |
Miscellaneous appliances including televisions,
VCRs, DVDs, cable/satellite boxes, cordless phones,
and home computers |
None |
| Site Generation |
Photovoltaic electric generation |
None |
The estimated annual
electrical and natural consumption in Table 1 was used
to calculate the estimated source energy consumption
and savings using the following equations:
Source MBTU = kWh * 3.412 * Me/1000 + therms * Mg/10
Where: Me = 3.16 = Site to source multiplier for electricity
(DOE, 2002b)
Mg = 1.02 = Site to source multiplier for natural
gas (DOE, 1995).
In Table 3, two columns estimate the savings percentage
for each end-use category realized in the pilot home
and compared to the benchmark and builder standard
homes. In the last two columns the estimated savings
for each end-use category realized in the pilot home
is determined as percentage of total source energy
used for either the benchmark or the builder standard
home.
The analysis determined that the pilot home built
to the design specifications (not including the contribution
of the photovoltaic system) will save 42% with respect
to the Building America Benchmark Definition and 35%
with respect to the Builder Standard Home for total
end-use source energy. These savings rise to 50% and
45% respectively when the contribution of the photovoltaic
system is included.
If plug loads were not considered, since homeowner
purchasing decisions determine the appliances selected,
the pilot home would save 47% with respect to the Building
America Benchmark Definition and 40% with respect to
the Builder Standard Home for source energy consumption.
Table 4. Summary of Estimated End-Use
Source Energy with Pilot Home Design
|
Annual Source Energy |
Estimated Source Energy Savings |
Percent of End Use |
Percent of Total |
End-Use |
BA Benchmark (MBTU) |
Builder Standard (MBTU) |
Pilot Home (MBTU) |
BA Benchmark |
Builder Standard |
BA Benchmark |
Builder Standard |
Space Heating |
87 |
74 |
38 |
56% |
49% |
17% |
14% |
Space Cooling |
60 |
43 |
26 |
57% |
39% |
12% |
6% |
DHW |
19 |
20 |
9 |
53% |
54% |
4% |
4% |
Lighting |
36 |
36 |
26 |
29% |
29% |
4% |
4% |
Appliances |
28 |
28 |
23 |
20% |
20% |
2% |
2% |
Subtotal |
230 |
201 |
121 |
47% |
40% |
38% |
31% |
Plug Loads |
58 |
58 |
47 |
19% |
19% |
4% |
4% |
Total Usage |
288 |
259 |
168 |
42% |
35% |
42% |
35% |
Site Generation |
- |
- |
-25 |
- |
- |
8% |
10% |
Net Energy Use |
288 |
259 |
143 |
50% |
45% |
50% |
45% |
Estimated savings
for different advanced system design improvements to
the pilot home with respect to the builder standard
are noted in Table 5. Energy costs are based on Swanee
EMC average rate for electricity of $0.07/kWh, and
Scana Energy average rate for gas of $.869/therm. A
discussion on the application, benefits, and costs
of different advanced system improvements follows.
Table 5. Estimated Savings for Incremental Improvements
with Pilot Home Design with respect to Builder
Standard
|
|
Builder Standard |
|
Site Energy |
Source Energy |
Energy Cost |
Measure Package |
Improvement Increment |
KWh |
therms |
MBTU |
Savings% |
$/yr |
Savings% |
Value ($/yr) |
Savings ($/yr) |
BA Benchmark |
17396 |
983 |
288 |
|
$2,072 |
|
|
|
Builder Standard (BS) |
15753 |
871 |
259 |
10% |
$1,859 |
|
|
|
(1) = BS + 2x4 Exterior Wall + Basement Improvements |
15406 |
714 |
239 |
8% |
$1,699 |
9% |
$161 |
$161 |
(2) = (1) + Air Infiltration Improvements |
15125 |
600 |
224 |
14% |
$1,580 |
15% |
$119 |
$280 |
(3) = (2) + Optimized & High
Performance HVAC |
14246 |
530 |
208 |
20% |
$1,457 |
22% |
$123 |
$402 |
(4) = (3) + Tankless DHW |
14247 |
424 |
197 |
24% |
$1,365 |
27% |
$92 |
$494 |
Final = (4) + Energy Efficient Lighting, Appliances |
11342 |
438 |
168 |
35% |
$1,181 |
37% |
$184 |
$679 |
Final + Site Generation |
9002 |
438 |
143 |
45% |
$1,017 |
45% |
$164 |
$842 |
Final + 2x6 Exterior Wall Improvements |
11257 |
369 |
160 |
38% |
$1,109 |
40% |
$71 |
$750 |
Exterior Wall Thermal
Performance
Exterior wall thermal performance improvements decrease
heating and cooling loads and increase homeowner comfort
and is focused on two areas: basements walls and main
floor walls.Since grade level for the pilot home slopes
from back to front it will have its basement walk out
at the front of the house. Basement walls are either
constructed of 6 in. thick concrete (against soil),
2x6 wood framing (at walk out area) or a combination
of both systems (at transition points in grade). A
total of 743 square feet of basement floor area is
finished. All concrete basement foundation walls will
be insulated on the inside with R-8 (1¼ in. thick)
polyisocyanurate foam board insulation glued directly
to the wall with 2x4 wood framing placed adjacent to
it and insulated with R-13 cellulose within cavities.
Wood framed basement walls will be insulated with R-13
cellulose. This practice is different from their current
practice, which consists of uninsulated walls in unfinished
basement areas (and the basement ceiling insulated)
or an insulated (R-13) wood frame wall installed around
the interior foundation wall perimeter in finished
basement areas. The foam board insulation will be applied
directly to the foundation wall and have its joints
sealed with a suitable tape thereby creating a vapor
retarder which limits the possibility of humid indoor
air interacting with a cooler foundation wall, thereby
reducing the potential for condensation to occur. The
builder estimates that there will be a $1,000 upgrade
cost (labor and materials) for using the directly applied
foam board insulation system. The main exterior walls
for the Hedgewood home will consist of exterior sheathing,
2x4 framing and R-13 cellulose insulation within cavities.
In the pilot home, R-3 (½ in. thick) extruded polystyrene
rigid board insulation sheathing will be used as much
as possible as the exterior sheathing material (wall
coverage was assumed to be about 40%). OSB will be
the exterior sheathing used for the balance of the
walls. No cost increase is expected for the insulating
sheathing usage. The predicted annual source energy
savings increment for all exterior wall thermal performance
improvements are 8% resulting in annual cost savings
of $161 for the homeowner. This saving was achieved
at a total upgrade cost of $4,000. Simple payback for
the improvement is 24.8 years.
2x6 Exterior Wall Thermal Performance Strategy
A strategy to improve the exterior wall’s thermal
performance beyond that exhibited in the pilot home
was considered. The strategy consisted of R-5 (1 in.
thick) extruded polystyrene rigid board insulation
sheathing applied over the entire wall surface. 2x6
wood framing installed at 24 in. centers with cavities
insulated to R-19 would complete the strategy. This
approach would result in annual source energy savings
increment of 3% with respect to the pilot home and
lead to $71 in additional annual cost savings for the
homeowner. The estimated upgrade cost for this strategy
is $1,000. Simple payback for the improvement is 14.1
years. This strategy would have to been used if energy
savings in end use areas such as appliances and plug
loads were not realized in order to achieve the minimum
40% total energy saving target.
Exterior Wall Durability Improvements
A strategy to improve the water shedding capability
of the exterior walls of the pilot home will be implemented.
A building envelope that has good water shedding capability
prevents rainwater entry into the wall assembly of
the house. Water in building assemblies can cause wood
rot or mold growth, which is not desirable from a durability
and indoor air quality perspective.A thorough strategy
for improving exterior wall durability was developed
and includes installing exterior sheathing closely
together to prevent water entry and applying plastic
house wrap overtop to create an effective drainage
plane. Integrating window and door flashing practices
with the drainage plane completes the strategy. Installation
of the drainage plane and flashing materials will promote
water movement away from the house. The builder estimates
that there will be a $200 upgrade cost (labor and materials)
for improving flashing practices. House wrap usage
is standard practice and no cost increase is expected.
Building Airtightness
Exterior walls that are more airtight have less outdoor
air coming through them and the exfiltration of conditioned
air is hindered. Large amounts of air leakage can adversely
affect comfort levels and increase energy consumption
in the house (to compensate for discomfort). Maintaining
continuity of the air barrier is critical for improving
airtightness in building envelope components. The main
air barrier would be on the inside face of exterior
walls and ceilings and consists of drywall. The use
of cellulose insulation in exterior walls is expected
to greatly lower air infiltration in that building
component. Draftstopping details were developed for
areas on exterior walls and ceilings that would not
normally be drywalled in order to make a continuous
air barrier. This included walls at bathtubs, behind
the fireplace and at the top of chases, which would
be insulated with fiberglass batts (and not benefit
from the use of celluloseinsulation). These measures
should result in fewer comfort complaints related to
drafts and temperature swings, which customers have
sometimes noticed in these areas. The numerous penetrations
through the envelope will be sealed as well. The builder
estimates that there will be a $150 upgrade cost for
draftstopping work and $300 in extra costs for sealing
of penetrations. The predicted annual source energy
savings increment for the building airtightness improvement
is 6% resulting in annual cost savings of $119 for
the homeowner. This saving was achieved at a total
upgrade cost of $450. Simple payback for the improvement
is 3.8 years, the second lowest of any improvement.
Optimized Heating and Cooling System
The high efficiency furnace (94% AFUE) and 14 SEER
condensing unit are energy efficiency upgrades for
Hedgewood. High efficiency equipment provides the same
amount of cooling or heating as lower efficiency equipment
but uses less energy in doing so. In order to promote
greater use of such equipment, a local HVAC supply
company donated Rheem® equipment for the project. An
engineered HVAC system analysis conducted on the pilot
home determined the heating and cooling loads for the
home. The thermal performance characteristics of the
home including exterior wall improvements, reduced
building envelope air leakage and effect of mechanical
ventilation were used to determine the heating and
cooling load. Since the home would be used as a model,
above average lighting usage was also assumed. Loads
were reduced to the extent that two separate HVAC systems,
the typical case for a home of this size, were no longer
needed. Furthermore, the one furnace used will be within
conditioned space, whereas in the typical case one
of the two units is located in the unconditioned attic.
A zone control system is being used, so that separate
areas of the home will be afforded individual temperature
and humidity control. Each floor, including the basement,
has its own zone. A furnace with 89,000 Btu/h output
was selected to provide heating. A 5-ton condensing
unit and evaporator coil were determined to be sufficient
to meet cooling loads, handle humidity and provide
adequate air distribution.If the load calculations
produced by the HVAC subcontractor, done to their typical
practice, were to be used, the total capacity of cooling
equipment installed would be 8 tons, with two units
being used instead of one. A 5-ton unit would only
serve the basement and first floor areas. A detailed
duct layout based on calculated loads and predicted
air flows was developed to ensure that correctly sized
ductwork could efficiently move air from the furnace
in the basement to all spaces that needed to be conditioned.
This approach is critical to ensure that comfort conditions
are maintained. To promote good distribution of cool
air in the summer on the second floor, while keeping
ductwork within conditioned space, a design strategy
of keeping duct registers in high wall locations was
initiated. But, due to the lack of suitable interior
framed walls on each floor to accommodate ductwork
pathways, this design strategy was abandoned. Instead
we decided (regretfully) that the only feasible way
to condition the second floor was through ducts traveling
through vented attic space to ceiling registers. To
facilitate the placement of the main duct truck leading
up to the attic space from the basement mechanical
room, an interior chase was designed. With some ductwork
in attic space, duct airtightness would be critical.
Therefore UL-181 approved mastic sealant is being installed
on all joints between all pieces of ductwork as well
as joints in the furnace, and joints between ductwork
and the furnace. A total air leakage goal of 10% for
the air distribution system has been established. No
more than 5% of air leakage can go to the outside.The
predicted annual source energy savings increment for
the optimized heating and cooling system improvement
is 6% resulting in annual cost savings of $123 for
the homeowner. The estimated upgrade cost for all HVAC
improvements, including mechanical ventilation (see
below), is $1,500. Simple payback for the improvement
is 12.2 years.
Mechanical Ventilation
Mechanical ventilation is needed to enhance indoor
air quality. It is particularly important to have a
mechanical ventilation system in an airtight home since
it receives a reduced amount of outdoor air through
natural infiltration.The builder will install a ventilation
and dehumidification unit. The unit will draw outdoor
air at an intermittent rate as governed by the ventilation
timer component of the control module. To meet ASHRAE
62.2 ventilation requirements, the house needs 70 cfm
of outdoor air on a continuous basis. In addition,
as determined by the humidity level set on the control
module, the unit will draw indoor air from a register
located in a breakfast area high wall location and
dehumidify it to the set point level. The EnergyGauge
USA analysis tool is not able to quantify the energy
usage of this system and its impact on air handler
run times due to its dehumidification performance,
therefore for energy modeling purposes the pilot home
was considered as having no ventilation system. As
noted in KAAX-3-33410-04.C.2.2, Detailed Field Test
Plan 2, we will evaluate the performance of the system
verses its energy consumption and recommend modeling
assumptions. The estimated upgrade cost for the mechanical
ventilation system for the pilot home is $1,000.
Domestic Hot Water Improvements
Two direct vent, tankless, gas-fired water heaters
with an EF of 0.85 will be installed. Each unit has
an input of 175.0 MBH and is capable for producing
4.7gallons per minute for a 60°F rise. (This assumes
a 60°F average ground water temperature for Atlanta
and a water outlet temperature of 120°F.) One unit
will be located in a second floor closet and serve
the hot water needs of the second floor, while another
unit will serve the balance of the house from its basement
location. Two tankless water heaters manufactured by
Bosch and donated to the project (retail cost $750
each) will be installed as per the builder’s request.
The builder is unfamiliar with this water heating technology
and remains cautious that one unit would have adequate
capacity to serve a house with four full bathrooms.
As noted in Detailed Field Test Plan 2, we will evaluate
if one tankless unit is sufficient to handle the hot
water load. A tankless water heater unit reduces the
energy consumption associated with domestic hot water
use because of its good recovery efficiency rating
and also because it eliminates the stand-by losses
associated with a large storage tank full of hot water.
Because the water heater is directly vented and has
minimal clearances to combustible products, it can
be located in many different places in the conditioned
space of the house. The predicted annual source energy
savings increment for the domestic hot water system
improvement is 4% resulting in annual cost savings
of $92 for the homeowner. This saving was achieved
at a total upgrade cost of $1,100 (which includes credit
for power vented hot water tank). Simple payback for
the improvement is 11.9 years.
Energy Efficient Lighting
We developed an advanced lighting systems plan for
the pilot home including exterior lighting. The plan
is a combination of two approaches and is based on
making improvements to hard-wired fixtures. The first
approach is a fixture change-out strategy that replaces
low efficiency incandescent fixtures with higher efficiency
fluorescent fixtures. The second approach is an advanced
residential lighting design that is a comprehensive
design of the lighting system based on the function
of the space and also architectural characteristics.
The design focuses on the use of energy efficient fixtures.
We estimate that 29% in source energy savings will
be realized by following the plan (refer to Table 3).
This savings level is based on an annual use schedule
developed for each fixture. The estimated upgrade cost
for all lighting improvements is $300.
Energy Efficient Appliances and Plug Loads
An Energy Star® labeled dishwasher, clothes washer,
and refrigerator are being installed in the pilot home.
Hot water usage is expected to decrease on average
by 4 gallons per day due to the Energy Star® labeled
dishwasher and 14 gallons per day due to the Energy
Star® labeled clothes washer. A clothes dryer that
is predicted to use less than 974 kWh/yr of energy
annually (the Building America Benchmark value for
this appliance) and a range/oven that uses less than
604 kWh/yr of energy annually (the Building America
Benchmark value for this appliance) will be installed.
It is estimated that these five appliances can be obtained
for a total annual energy use not to exceed 2000 kWh/yr.
This will result in 20% energy savings from the appliance
end use category.In order to reduce plug loads, other/miscellaneous
Energy Star® labeled appliances will be installed in
the pilot home (when it will be used as a model) and
suggested for use to the eventual homeowner. Other/miscellaneous
appliances include televisions, VCRs, DVDs, cable/satellite
boxes, cordless phones, and home computers. Assuming
that three televisions will be installed, it is estimated
that 1,000 kWh/yr of energy savings, with respect to
the Building America Benchmark value, can be achieved
in the plug loads end use category.No additional costs
to the builder are predicted for using energy efficient
appliances since they are widely available. The predicted
annual source energy savings increment for energy efficient
lighting, appliance and plug load improvements is 11%
resulting in annual cost savings of $184 for the homeowner.
These improvements collectively represent the measure
with the largest energy savings impact and can be obtained
at an estimated upgrade cost of $300. Simple payback
for the improvement is 1.6 years, the lowest of any
improvement.
Photovoltaic System
High efficiency solar modules will provide electricity.
The system will be connected to the utility grid to
allow for net metering. The system will have a maximum
power output of 2 kW and sit on the home’s roof. We
estimated annual production of electricity to be 2,864
kWh. The estimated cost for the photovoltaic system
is $13,000. The predicted annual source energy savings
increment for the photovoltaic system improvement is
10% resulting in annual cost savings of $164 for the
homeowner. Simple payback for the improvement is 79.3
years, the highest of any improvement. |